If 2 workers finish a task in 4 days, how many days will 4 equal workers need?

A) 5/2 days

B) 3/2 days

C) 3 days

D) 2 days

Answer: D

Explanation: For the same job, workers × time stays constant when rates are equal.
Using the values in this question gives 2 days as the correct answer.