The Success Center Mithi

If 8 workers finish a task in 10 days, how many days will 16 equal workers need?

A) 11/2 days

B) 5 days

C) 9/2 days

D) 6 days

Answer: B

Explanation: For the same job, workers × time stays constant when rates are equal.
Using the values in this question gives 5 days as the correct answer.