Question: If 4 equally productive workers finish a task in 10 days, how many worker-days does it require?
- 40 worker-days
- 41 worker-days
- 39 worker-days
- 42 worker-days
Correct Answer: A — 40 worker-days
Explanation: Worker-days = number of equal-rate workers × days worked.
Using the values in this question gives 40 worker-days as the correct answer.