Question: If 6 equally productive workers finish a task in 12 days, how many worker-days does it require?
- 72 worker-days
- 73 worker-days
- 71 worker-days
- 74 worker-days
Correct Answer: A — 72 worker-days
Explanation: Worker-days = number of equal-rate workers × days worked.
Using the values in this question gives 72 worker-days as the correct answer.